Contract No: HK/2011/07 Wanchai
Development Phase II and Central Wanchai Bypass Sampling, Field Measurement and Testing Work (Stage 2) Environmental Permit
no. EP-122/2002/D Monthly
Environmental Monitoring & Audit Report
- JULY 2014 -
|
CLIENTS: |
|
Civil Engineering and
Development Department |
Lam Geotechnics Limited 11/F Centre Point 181-185
Gloucester Road, Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
August 2014 |
2.2 Scope
of the Project and Site Description
2.3 Project
Organization and Contact Personnel
3 status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
5.2 Air
Quality Monitoring Results
6.3 Review
of the Reasons for and the Implications of Non-compliance
6.4 Summary
of action taken in the event of and follow-up on non-compliance
7 Cumulative
Construction Impact due to the Concurrent Projects
9 Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule 2 Designated Projects under this Project
Table 2.2 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2012/08
Table 4.1 Continuous Noise Monitoring Stations
Table 4.2 Air Quality Monitoring Stations
Table 5.1 Continuous Noise Monitoring Stations for Contract
no. HK/2012/08
Table 5.2 Air Quality Monitoring Station for Contract no.
HK/2012/08
Table 5.3 Details of Waste Disposal for Contract no.
HK/2012/08
Table 8.1 Summary of Environmental Inspections for Contract
no. HK/2012/08
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
LIST OF FIGURES
Figure 2.1 Project Layout
Figure 2.2 Project Organization Chart
Figure 4.1 Locations of
Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Continuous Noise Monitoring
Results and Graphical Presentations
Appendix 5.3 Air Quality
Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification
of Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HK/2012/08
– Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West
·
Diaphragm wall construction works
·
Pipe pile wall construction
Noise Monitoring
Air Quality Monitoring
Complaints, Notifications of Summons and Successful
Prosecutions
Site Inspections and Audit
Future Key Issues
Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan
Chai Bypass at Wan Chai West
·
Diaphragm wall construction works
·
Pipe pile wall construction
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed take up the role as the
Environmental Team (ET) under Environmental Permit no. EP-122/2002/D to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Central Reclamation Phase III - Studies, Site
Investigation, Design and Construction (Register No.: AEIAR-040/2001) since 1 May 2013.
1.1.2.
This report documents the finding of EM&A
works for Environmental Permit (EP) no.
EP-122/2002/D, during the period of July 2014. The
cut-off date of reporting is the last day of each reporting month.
Section 1 Introduction – details the scope and structure of the report.
Section 2 Project
Background – summarizes background and
scope of the project, site description, project organization and contact
details of key personnel during the reporting period.
Section 3 Status of Regulatory Compliance – summarizes the status of valid Environmental Permits /
Licenses during the reporting period.
Section 4 Monitoring
Requirements – summarizes all monitoring
parameters, monitoring methodology and equipment, monitoring locations,
monitoring frequency, criteria and respective event and action plan and
monitoring programmes.
Section 5 Monitoring
Results – summarizes the monitoring
results obtained in the reporting period.
Section 6 Compliance Audit – summarizes
the auditing of monitoring results, all exceedances environmental
parameters.
Section 7 Cumulative Construction Impact due
to the Concurrent Projects – summarizes the relevant cumulative
construction impact due to the concurrent activities of the concurrent Projects.
Section 8 Site
Inspection – summarizes the findings of
weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints,
Notification of summons and Prosecution – summarizes the cumulative statistics on complaints, notification of summons and
prosecution
Section 10 Conclusion
2.1.1
Central Reclamation Phase III - Studies, Site
Investigation, Design and Construction (hereafter called “the Project”) are
Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Reports for
Central Reclamation Phase III - Studies, Site Investigation, Design and
Construction (Register No. AEIAR-040/2001) has been approved on 31 August 2001.
2.2.1.
The design and construction of Central
Reclamation Phase III involves the permanent reclamation and construction and
operation of a trunk road and its road tunnel that is shown at Figure 2.1.
2.2.2.
The key purpose of the study area encompasses the area of Victoria Harbour to the southeast of
the new Outlying Islands Ferry Piers and north of Edinburgh Place and Lung Wui
Road. The area extends eastward to Fenwick Pier Street and the Fleet Arcade,
and includes the existing GPO, Star Ferry Piers, Queens Pier, City Hall, PLA
Headquarters, Hong Kong Red Cross Headquarters building and the Tamar Site. The scope of the Central Reclamation, Phase III includes:
·
Reclamation
and seawalls, roads and associated services, North Island Line Protection Works
and Advance Trunk Road Tunnel (ATRT) for the CWB;
·
Reprovisioning
of Star Ferry Pier, public landing steps, wallah wallah moorings, and motor
boat/launch operators' kiosks;
·
External
cooling water systems which consist of the cooling water pumping shells for
future developments, and the reprovisioning of existing cooling water pumping
stations and associated pipework systems and E&M works;
·
Reprovisioning
of existing Leisure and Cultural Services Department (LCSD)'s facilities;
·
Provision
of a flood relief path, stormwater culvert extensions, upgrading of hinterland
stormwater drainage resulting from the reclamation, demolition of the existing
waterfront structures and necessary landscaping;
·
The
Hong Kong Station Extended Overrun Tunnel (EOT) and associated ventilation
structures entrusted for construction within the CRIII works;
·
Reprovisioning
of the Government Heliport at the Wan Chai PCWA and reprovisioning of the Wan
Chai PCWA at Chai Wan Basin.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be
either constructed or operated. Table 2.1 summarises the four
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
DP1
|
Central-Wanchai
Bypass (CWB) |
Schedule
2, Part I, A.7 |
DP2
|
Road
P2 and other roads which are classified as primary/district distributor roads
|
Schedule
2, Part I, A.1 |
DP3
|
Reclamation
works |
Schedule
2, Part I, C.1 |
DP4 |
The
North Island Line (NIL) Protection Works within CRIII |
Schedule
2, Part I, A.7 |
2.2.4.
The designated project work I (DP1) was
awarded to China State-Leader Joint Venture HK/2012/08 as part of the Project
works by the Civil Engineering and Development Department (CEDD). The construction work under Contract no. HK/2012/08 was commenced on 27
May 2013.
2.3.1
Civil
Engineering and Development Department is the overall project controllers for the Central Reclamation Phase III Project. For
the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.3.2
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are
summarized in Table 2.2:
Table 2.2 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s
Representative for WDII |
Principal
Resident Engineer |
Mr.
Frankie Fan |
2587
1778 |
2587 1877 |
Engineer’s
Representative for CWB |
Principal
Resident Engineer |
Mr.
Peter Poon |
3922
3388 |
3912 3010 |
|
China
State- Leader JV |
Contractor
under Contract no. HK/2012/08 |
Project Director |
Mr.
Andrew
Tse |
9137 1811 |
2877 1522 |
Project Manager |
Mr.
Victor
Wu |
9193 8871 |
|||
Deputy Project Manager |
Mr. Eddie Chung |
9189 8118 |
|||
Site Agent |
Mr.
Paul
Lui |
9095 7922 |
|||
Environmental Officer |
Mr.
James
Ma |
9130 9549 |
|||
Environmental Supervisor |
Mr. Y. L. HO |
9856 5669 |
|||
ENVIRON
Hong Kong
Limited |
Independent Environmental
Checker (IEC) |
Independent Environmental
Checker (IEC) |
Mr.
David Yeung |
3465
2888 |
3465
2899 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr.
Raymond
Dai |
2882 3939 |
2882 3331 |
2.3.3
In
this reporting month, the principal work activities of the contract is included
as follows:
Contract no. HK/2012/08 – Wan Chai Development
Phase II – Central- Wan Chai Bypass at Wan Chai West
·
Diaphragm wall construction works
·
Pipe pile wall construction
2.3.4
In
coming reporting month, the principal work activities of the contract is
anticipated as follows:
Contract no.
HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai
West
·
Diaphragm wall construction works
·
Pipe pile wall construction
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-122/2002/D |
1 Sep 2009 |
Valid |
3.1.2.
The current status on licences and/or permits on environmental
protection pertinent for contract no. HK/2012/08 showed in Table 3.2.
Table
3.2 Cumulative Summary of Valid Licences and Permits under Contract no.
HK/2012/08
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid Period/ Expiry Date |
Status |
Notification
of Works Under APCO |
355439 |
4
Feb 2013 |
N/A |
Valid |
Registration
as a Chemical Waste Producer |
5213-134-C3790-01 |
8
Mar 2013 |
N/A |
Valid |
Billing
Account under Waste Disposal Ordinance |
7016883 |
18 Feb 2013 |
18 Jul 2017 |
Valid |
Billing
Account under Waste Disposal Ordinance (Dumping by Vessel) |
- |
- |
- |
- |
Construction Noise Permit |
GW-RS0257-14 |
26 Mar 2014 |
28 Mar 2014 to |
Valid |
Water Discharge Licence |
WT00018470-2014 |
6 Mar 2014 |
31 Mar 2019 |
Valid |
3.1.3.
Implementation status of the recommended mitigation measures during this
reporting month is presented in Appendix 3.1.
NOISE Monitoring Stations
4.1.1.
The continuous noise monitoring station for the Project is listed and
shown in Table 4.1 and Figure
4.1.. Appendix
4.1 shows the established Action/Limit
Levels for the monitoring works.
Table 4.1 Continuous Noise
Monitoring Stations
District |
Station |
Description |
Central |
ACL3 |
City
Hall |
Noise Monitoring
Parameters, Frequency and Duration
4.1.2.
Continuous 24-hour noise
monitoring shall be carried out at the designated monitoring stations. The
following is an initial guide on the regular monitoring frequency for each
station on a 24 hours daily basis when noise generating activities are
underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on every day.
4.1.3.
If construction works are extended to include
works during the hours of 1900 – 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.4.
As referred to in the Technical Memorandum ™
issued under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agrees to within 1.0 dB.
4.1.5.
Noise measurements shall not be made in fog,
rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10
m/s. The wind speed shall be checked with a portable wind speed meter capable
of measuring the wind speed in m/s.
4.1.6.
The sound level meter shall be checked using
an acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit.
Measurements will be accepted as valid only if the calibration level from
before and after the noise measurement agrees to within 1.0 dB.
Air Quality Monitoring
Stations
4.2.1.
The air quality monitoring stations for the
Project are listed and shown in Table 4.2 and Figure 4.1.. Appendix 4.1 shows the
established Action/Limit Levels for the monitoring works.
Table 4.2 Air Quality Monitoring Stations
Station ID |
Description |
ACL1 |
City Hall |
ACL2a |
Contractor HK/2012/08 Site Office |
Air QUALITY Monitoring
Parameters, Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance with
the following specifications shall be used for carrying out the 1-hour and
24-hour TSP monitoring:
·
0.6
– 1.7 m3 per minute adjustable flow range;
·
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable
of providing a minimum exposed area of 406 cm2;
·
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped
with a shelter to protect the filter and sampler;
·
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
Equipped
with a flow recorder for continuous monitoring;
·
Provided
with a peaked roof inlet;
·
Incorporated
with a manometer;
·
Able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
Easily
changeable filter; and
·
Capable
of operating continuously for a 24-hour period.
4.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly
intervals. The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference.
All the data should be converted into standard temperature and pressure
condition.
Laboratory Measurement /
Analysis
4.2.7.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
Filter paper of size 8” x 10” shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
4.2.9.
After sampling, the filter paper loaded with
dust shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
4.2.10.
All the collected samples shall be kept in a
good condition for 6 months before disposal.
4.2.11.
Current calibration certificates of equipment
are presented in Appendix 4.2.
5.0.1.
The environmental monitoring will be
implemented based on the division of works areas of each designated project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing work
areas of various contracts, latest status of work commencement and monitoring
stations is shown in Figure 2.1 and Figure 4.1. The
monitoring results are presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent
contract is:
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central – Wan Chai Bypass at
Wan Chai West.
5.0.3.
The environment monitoring schedules for
reporting month and coming month are presented in Appendix
5.1.
5.1.1
Due to safety concerned, the location of the continuous noise monitoring
station at City Hall was finely adjusted to the roof of the City Hall, Low
Block on 1 May 2013.
5.1.2
The proposed division of noise monitoring stations is summarized in
Table 5.1 below.
Table 5.1 Continuous Noise Monitoring Stations
for Contract no. HK/2012/08
Location
ID |
District |
Description |
ACL3 |
Central |
City Hall |
Remarks: Continuous noise monitoring results
and graphical presentation for ACL3 during restricted hours and night time
period are for information only.
5.1.3
Limit level exceedances were recorded on
22 July 2014 during daytime in the reporting month. After checking with
Contractor, no major noisy construction activity was conducted on 22 July 2014.
In addition, thunderstorm warning for the concern location and amber rainstorm
warning were hoisting during the recorded period. As such, the exceedances were
considered to be contributed by the adverse weather condition and not related
to Project.
5.1.4
Continuous noise monitoring results measured in this reporting period
are reviewed and summarized. Details of continuous noise monitoring results and
graphical presentation can be referred to Appendix
5.2.
5.2.1
The proposed division of air quality
monitoring stations are summarized in Table 5.2 below.
Table 5.2
Air
Quality Monitoring Station for Contract no. HK/2012/08
Station |
Description |
ACL1 |
City Hall |
ACL2a |
Contractor HK/2012/08 Site Office |
5.2.2
Due to electricity supply, the 24hr TSP monitoring at monitoring station
ACL1 was rescheduled form 28 July 2014 to 29 July 2014
5.2.3
Due to the defective electricity
supply found at monitoring station ACL1 and the advice from City Hall Building
Management, the air monitoring station ACL1 – City Hall was finely adjusted on
28 Feb 2014 to an alternate electricity supply.
5.2.4
Due to the large scale renovation works at
People’s Liberation Army Headquarter, a Proposal for Relocation of Air Quality
Monitoring Station at People’s Liberation Army Headquarter (ACL2) was formally
submitted to EPD on 4th November, 2013.
5.2.5
Air Quality Monitoring at ACL2 was
temporarily suspended during the period from 14th November, 2013 to 3rd December,
2013.
5.2.6
The Proposal for Relocation of Air Quality
Monitoring Station at People’s Liberation Army Headquarter (ACL2) was approved
by EPD on 27 November 2013.
5.2.7
According to the approved proposal for
relocation of Air Quality Monitoring station, the action and limit levels of
ACL2a shall adopt the reference monitoring result from the baseline air
monitoring report for EP/364/2009 in 22 April 2010 in which approved by EPD.
5.2.8
The air quality monitoring at ACL2a –
Contractor HK/2012/08 Site Office was commenced on 7 December 2013.
5.2.9
No action or limit level exceedance was
recorded at ACL1 – City Hall and ACL2a – Contractor HK/2012/08 Site Office in
the reporting month.
5.2.10
The air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix
5.3.
5.3.1
Inert and non-inert C&D wastes were disposed
in this reporting month. Details
of the waste flow table are summarized in Table 5.3.
Table
5.3 Details
of Waste Disposal for Contract no. HK/2012/08
Waste Type |
Quantity this month |
Cumulative
Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
0 1484 |
396 4144 |
TM38 TKO137 |
Inert C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Non-inert C&D materials disposed, m3 |
45 |
305 |
SENT
Landfill |
Non-inert C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Chemical waste disposed, kg |
NIL |
NIL |
NIL |
6.0.1.
The Event Action Plan for construction noise
and air quality are presented in Appendix 6.1.
6.1.1.
Limit level exceedances were recorded on 22 July 2014 during daytime in
this reporting month. After the investigation, the exceedances were concluded
as non-project related.
6.2.1.
No action or limit level exceedance was
recorded at ACL1 – City Hall and ACL2a – Contractor HK/2012/08 Site Office in
this reporting month.
6.3.1.
There was no non-compliance from the site
audits in the reporting period. The observations and recommendations made in
each individual site audit session were presented in Section 8.
6.4.1
There was no particular action taken since no
non-compliance was recorded from the site audits in the reporting period.
7.0.1.
This section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III (CRIII), Wan Chai
Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern
Corridor Link projects (IECL) and Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel).
7.0.2.
According
to the Final EM&A report of Central Reclamation Phase III (CRIII) for
Contract HK 12/02, the major construction activities were completed by end of
January 2014 and no construction activities were undertaken thereafter and the
water quality monitoring was completed in October 2011. As such, it is considered that there were no
cumulative construction impact due to the concurrent activities of the current
projects with the Central Reclamation Phase III (CRIII) undertaken by
contractor HK12/02 in the reporting month.
7.0.3.
According to the construction programme of
Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern
Corridor Link projects, the major construction activity under Wan Chai
Development Phase II were marine
works at HKCEC areas, tunnel works at Wan Chai East and filling works at Wan
Chai West. The major construction activities under Central-Wan
Chai Bypass and Island Eastern Corridor Link Projects were backfilling works at
TS4 and TPCWAE. Bridge construction and tunnel works at Central Interchange,
ELS, segment launching works and tunnel works at North Point area. The major
environmental impact was water quality impact at Causeway Bay and Wan Chai.
Marine-based construction activities were filling works at WanChai West and
removal of temporary reclamation at TS4, TS2 and EX-PCWA at Wan Chai East in
the reporting month.
7.0.4.
No significant air impact from construction
activities was anticipated in the reporting month. Besides, no project-related
exceedances were recorded during the air and noise environmental monitoring
events in the reporting month. Thus, it is evaluated that the cumulative
construction impact from the concurrent projects including Central Reclamation
Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass
(CWB), Island Eastern Corridor Link projects (IECL) was insignificant.
8.0.1.
Five site
inspections for Contract no. HK/2012/08 were carried out on 2, 8, 14, 22 and 30
July 2014 in the reporting month. The
results of inspection and outcome are summarized in Table 8.1
Table 8.1 Summary
of Environmental Inspections for Contract no. HK/2012/08
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
140708_01 |
8-July-14 |
Oil
cans should be placed on drip tray. |
Drip trap was
provided for oil cans |
Completion
as observed on 14 July 2014 |
9.0.1. No
environmental complaint was received in the reporting period.
9.0.2.
The details of cumulative complaint log and updated summary of
complaints are presented in Appendix 9.1
9.0.3. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table 9.1 Cumulative Statistics on Complaints
Reporting
Period |
No.
of Complaints |
June 2013 – June 2014 |
0 |
July 2014 |
0 |
Total |
0 |
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Environmental
Parameters |
Cumulative
No. Brought Forward |
No.
of Successful Prosecutions this month (Offence Date) |
Cumulative
No. Project-to-Date |
Air |
0 |
0 |
0 |
Noise |
0 |
0 |
0 |
Water |
0 |
0 |
0 |
Waste |
0 |
0 |
0 |
Total |
0 |
0 |
0 |
10.0.1.
The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2.
The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1. The construction programmes of individual contracts are provided
in Appendix 10.1.
Table
10.1 Summary of Key
Construction Activities of Individual Contract(s) to be commenced in Coming
Reporting Month
Contract No. |
Key Construction
Works |
Recommended Mitigation Measures |
HK/2012/08 |
·
Diaphragm wall construction works ·
Pipe pile wall construction |
·
Dust control during dust generating works; ·
Implementation of proper noise pollution control; and ·
Provision of protection to ensure no runoff out of site area or
direct discharge into public drainage system. |